Westminster waste depot costs soar to £13.5m
Unexpected ground conditions force significant increase in project budget for new electric vehicle fleet.
Incident → evidence → outcomeThe projected cost for Westminster City Council's new waste depot at Mandela Way has risen to £13.5 million, a significant increase from the initial estimate of £6.6 million. This escalation is attributed to the discovery of unexpected subsurface conditions that necessitate substantial alterations to the planned foundations and drainage systems.
Supporting Electric Vehicle Fleet
The depot, located just off Old Kent Road in Bermondsey, is a key component of the council's strategy to transition to a fully electric waste collection fleet. Once completed, it will provide essential facilities for waste collection and vehicle storage, designed to support around 40 new electric refuse collection vehicles. This initiative aligns with the council's commitment to achieving carbon neutrality by 2030.
Political Disagreement Over Costs
The project's budget increase has led to political friction. Westminster's Conservative administration has criticised the previous Labour administration, which approved the provisional budget in May 2024, for what they term a "due diligence failure". Council Leader Paul Swaddle stated that taxpayers are facing an additional £7.97 million bill due to the initial lack of ground investigation, money he suggested could be better used for public services.
Councillor Ellie Ormsby, Leader of the Opposition, defended the original estimate, explaining to MyLondon that the £6.6 million figure was based on early feasibility studies and was explicitly described as 'notional' and 'provisional'. She stated that the ground investigations subsequently revealed issues that would have impacted foundations and drainage, leading to the cost increase as the project requirements became clearer. Ormsby accused the Conservatives of "manufacturing outrage" and suggested they focus on their own review findings.
Project Timeline and Next Steps
The original early feasibility estimate for the Mandela Way project was approved by Westminster Labour in May 2024. This was part of a larger £7.6 million budget that also included a cleansing depot at Harewood Avenue in Marylebone. The Mandela Way depot must be completed by September 2027 to coincide with the start of the council's new waste and management contract, leaving no scope for further delays. The current decision is subject to a call-in period, which concludes on September 3.
Questions this report answers
01How much is the new Westminster waste depot expected to cost?
The new waste depot at Mandela Way is now predicted to cost £13.5 million. This is an increase from the original estimate of £6.6 million, with the additional costs attributed to unexpected subsurface conditions requiring significant foundation and drainage work.
02Why has the cost of the waste depot project increased?
The cost has increased due to unexpected subsurface conditions discovered during ground investigations. These issues require significant changes to the foundations and drainage systems, leading to higher construction expenses than initially anticipated.
03What is the purpose of the new waste depot?
The depot will support Westminster City Council's transition to a fully electric waste fleet. It will provide facilities for waste collection and storage for approximately 40 new electric refuse collection vehicles, contributing to the council's carbon neutral commitments.
04When does the decision on the waste depot project need to be finalised?
The decision regarding the Mandela Way waste depot is subject to a call-in period, which is scheduled to end on September 3. The depot itself needs to be completed by September 2027 to align with the council's new waste and management contract.
Support is available without a police report
Find London services, specialist support and the rights set out in the Victims’ Code. If someone is in immediate danger, call 999.
Find victim supportSend a correction or case update
If a hearing, charge or outcome has changed, send the court, case number and source document so we can update the record.
Contact the deskContinue the investigation
Community SafetyWestminster Council blunder leads to family eviction
Fraud & CybercrimePimlico fraudster ordered to repay £494k for illegal subletting
Community SafetyHillingdon Council approves two homes to be converted into flats
Community SafetyEpping Forest fungi pickers warned by City Corporation