Wates Construction appointed to complete phase 2b after contractor Ardmore entered administration.

Reporting desk London Crime News Desk||3 min read|London Crime News
Hackney Council to Spend £30m on Stalled Britannia ProjectIncident → evidence → outcome
Hackney Council to Spend £30m on Stalled Britannia ProjectLondon Crime News

Hackney Council is set to allocate £30 million to resume the final stage of the Britannia Project, located in Shoreditch Parkside. The project's last phase, known as 2b, was halted in June when its main contractor, Ardmore Construction Group Ltd, entered administration. This intervention by the council aims to prevent further financial losses and provide clarity to stakeholders.

Wates Construction Ltd has been appointed to complete the next stage of works for an estimated £30.1 million. This contract, approved on November 2, includes VAT and covers making the buildings watertight and purchasing critical construction materials, alongside site management. The original completion date for phase 2b was late 2026.

Increased Project Costs

The total cost of the Britannia regeneration is now likely to exceed its revised budget of £196.8 million. When initially approved in 2018, the entire masterplan was estimated at £384 million. Phase 2b was first estimated at £153.9 million in 2023, but the council now anticipates costs surpassing the revised budget.

The final phase of the development will deliver 371 homes in total. This includes 51 homes designated for social rent, 30 shared ownership properties, and 290 flats for sale at market rate. These market-rate flats are intended to help fund the leisure centre, affordable housing, and a new school associated with the regeneration.

The collapse of Ardmore Construction Group Ltd in June followed a High Court ruling that made the company liable for £14.9 million in historic claims related to cladding safety. Hackney Council's Executive Director of Housing, Rickardo Hyatt, stated that restarting the project quickly is essential to mitigate further financial impact and limit losses.

Future Contract Awards

Councillor Alastair Binnie-Lubbock, Cabinet Member for Regeneration, Planning and Inclusive Neighbourhoods, indicated a phased approach to completing the project. The council expects a second contract award in Spring 2027 for internal works and landscaping, which will be brought before the Cabinet Procurement and Insourcing Committee for approval.

The Britannia Masterplan began in 2016, transforming 3.2 hectares of council-owned land. Previous phases have delivered a new leisure centre, the City of London Academy Shoreditch Park secondary school, and new public spaces. The social rent homes in the final phase will be used to rehouse some residents from the Colville Estate.

Reader briefing

Questions this report answers

Q/A
01How much is Hackney Council spending on the Britannia Project?

Hackney Council is set to allocate £30 million to restart the final phase of the Britannia Project. This funding is part of a £30.1 million contract awarded to Wates Construction Ltd to complete the works.

02Why did the Britannia Project stall?

The final phase of the Britannia Project stalled in June after the council's main contractor, Ardmore Construction Group Ltd, entered administration. This followed a High Court ruling making the company liable for significant historic claims regarding cladding safety.

03What is the total expected cost of the regeneration?

The total cost of the Britannia regeneration is now likely to exceed its revised budget of £196.8 million. The project's initial estimate in 2018 was £384 million, with phase 2b initially costed at £153.9 million in 2023.

04What will the final phase of the project deliver?

The final phase of the Britannia Project will deliver 371 homes. These include 51 social rent homes, 30 shared ownership properties, and 290 market-rate flats. The project also includes a leisure centre, a secondary school, and public spaces.

LC
Source-led case desk

London Crime News Desk

Source-led, editor-supervised

See the reporting protocol →
Help after crime

Support is available without a police report

Find London services, specialist support and the rights set out in the Victims’ Code. If someone is in immediate danger, call 999.

Find victim support
Secure the detail

Send a correction or case update

If a hearing, charge or outcome has changed, send the court, case number and source document so we can update the record.

Contact the desk

Continue the investigation

Who else reported this

Our article above is written from the facts in these reports. Read the originals — every one is linked.

The morning case file

London Crime Briefing

Significant incidents, hearings, outcomes and public-data changes across the capital.

Hackney Council Britannia Project £30m | London Crime News